Lea Valley Business Park, Enfield

Portland St, Manchester
March 19, 2019

Client

HSBC Bank Pension Trust (UK)

Value

£3,000,000

Location

Edmonton, London

Duration

26 Months

Information

After much negotiations and a thorough tender process we were awarded the full demolition and asbestos removal works.

The site consisted of vast industrial warehousing units and a high rise office tower which sat next to one of London’s busiest roads, the North Circular. having removed all the asbestos materials from the buildings we commenced the demolition works. using our fleet of machines on this site from 20 tone to our specialist high reach machine with various attachments.

With this site being bounded by a major road on one side and a canal the other there had to be a lot of planning and discussions on the safest way to complete the works without affecting either. our site team and staff meet with the council HSE and the client to show our plans on how we were going to demolish the buildings in a safe manner. all parties were more than leased with our designs and gave us the go ahead.

Having completed the project 2 weeks ahead of program and the way we have handled this project not just safely but professionally our client has now gave us 2 more phases to demolish on the industrial park

Works Involved

  • High Reach demolition of a tower block
  • Demolition of industrial units
  • Asbestos removal
  • Crushing of all arising materials